What documents are required when applying to connect a new generation source to the power grid?
An application to connect a new generation source to the power grid requires both formal and technical documentation related to the investment.
- Document confirming legal title to the land – lease agreement and Land and Mortgage Register (Land Registry) number, or the Land and Mortgage Register number/current extract from the land register
- Site development plan on a topographic map indicating the proposed installation location
- Excerpt and map from the Local Spatial Development Plan or a Zoning Decision (Decision on Land Development Conditions)
- Selected equipment – manufacturer, model, power rating, quantity, together with technical datasheets, certificates, declarations of conformity, and harmonic/power quality charts (or proposed by NEZE)
- Applicant’s details
- Power of Attorney (if the application is submitted by NEZE on the applicant’s behalf)
- Single-line electrical diagram (or prepared by NEZE)
- Expected date of commencement of electricity supply/consumption
- Bank account number and bank name (for payment of the required advance fee)
- Proof of payment of the application fee