| STAGE 0 (ADMINISTRATIVE) – Collection of Project Documentation and Data | ||
|---|---|---|
| 0.1 | Contract execution | Client / NEZE |
| 0.2 | Collection of documentation in accordance with the checklist | Client |
| 0.3 | Preparation of the equipment modification application | NEZE |
| 0.4 | Review of the equipment modification application | DSO |
| STAGE 1 (DESIGN) – Design and Administrative Activities | ||
|---|---|---|
| 1.1 | Grid connection design – documentation preparation | NEZE |
| 1.2 | Grid connection design – approval process | NEZE / DSO |
| 1.3 | Operational Cooperation Instructions (IWR) | NEZE / DSO |
| 1.4 | Testing and Commissioning Schedule (HPiT) | NEZE / DSO |
| STAGE 2 – IMPLEMENTATION | |||
|---|---|---|---|
| 2.2 | Transformer Substation Delivery | ||
| 2.2.1 | Delivery of transformer substation / R_GEN | NEZE | |
| 2.2.2 | Installation of transformer substation / R_GEN | NEZE | |
| 2.3 | I/O CABINET DELIVERY AND INSTALLATION | ||
| 2.3.1 | I/O cabinet installation in RG_BESS / GPZ / GPO / ST | NEZE | |
| 2.4 | METERING SYSTEM UPGRADE | ||
| 2.4.2 | Delivery and installation of the metering system | NEZE | |
| 2.5 | COMMISSIONING OF PROTECTION SYSTEMS (EAZ) AND TELECONTROL | ||
| 2.5.1 | Protection relay configuration in the MV switchgear | NEZE | |
| 2.5.2 | Uploading protection settings | NEZE | |
| 2.5.3 | Verification of protection logic, automation and interlocks | NEZE | |
| 2.5.4 | Testing protection settings implemented by the PV/CHP/BESS/WT supplier | NEZE | |
| 2.5.5 | MSG modem configuration | NEZE | |
| 2.5.6 | Scheduling and performing communication tests with the DSO | NEZE | |
| 2.5.7 | Telecontrol verification report with the DSO | NEZE / DSO | |
| 2.6 | PV/CHP/BESS/WT System Configuration | ||
| 2.6.1 | Delivery of complete documentation and technical information from the BESS / PV / WT supplier (supplier contact details and commissioning procedure) | Client | |
| 2.6.2 | Commissioning and configuration works, including support for PV/CHP/BESS/WT service engineers | NEZE | |
| 2.6.3 | SCADA system for market functions – DATAMATIC? | Client | |
| 2.7 | ENERGIZATION – GRID CONNECTION OF THE FACILITY | ||
| 2.7.1 | Preparation and submission of the Distribution Services Agreement application | NEZE | |
| 2.7.2 | Review of electricity supplier offers | Client | |
| 2.7.3 | Execution of agreements: Distribution Services Agreement (with the DSO) Electricity Purchase Agreement (any supplier with a BRP) Electricity Sales Agreement (any supplier with a BRP) Balancing Agreement (BRP) (any supplier with a BRP) | Client / DSO | |
| 2.7.4 | Electricity supplier agreement becomes effective | Client | |
| 2.7.5 | Completion of commissioning documentation and notification of readiness for acceptance | NEZE | |
| 2.7.6 | Technical inspection by the DSO | NEZE / DSO | |
| 2.7.7 | Commissioning of the installation | NEZE | |
| STAGE 3 – POST-COMPLETION | ||
|---|---|---|
| 3.1 | AS-BUILT DOCUMENTATION | |
| 3.1.1 | Compilation and printing of as-built documentation | NEZE |
| 3.1.2 | As-built documentation (redline corrections) | NEZE |
| 3.1.3 | Formal procedure for obtaining FON (Final Operational Notification) | NEZE |
| 3.2 | SERVICE Maintaining the 2-year warranty (including the supply and replacement of consumable components such as power supplies, batteries, etc.) | |
| 3.2.1 | Service 1-1 | NEZE |
| 3.2.2 | Service 1-2 | NEZE |
| 3.2.3 | Service 2-1 | NEZE |
| 3.2.4 | Service 2-2 | NEZE |