oPNU Approval Process in Accordance with NC RfG
The NC RfG compliance process includes the following steps:
- Schedule the testing date with the DSO dispatcher
- Install the power quality analyzer at the point of connection (transformer substation or HV/MV substation)
- Perform power quality measurements (the measurement period depends on the DSO’s requirements and solar irradiance conditions)
- Perform background measurements (with the generation source disconnected)
- Carry out compliance tests, including:
- Determining the generation source characteristics as a function of solar irradiance (for PV installations)
- Generation source start-up tests
- Generation source shutdown tests
- Assessment of the power plant’s impact on power quality
- Verification of voltage (U) and reactive power (Q) control functions, active power limitation, and voltage regulation response time
- Verification of automatic disconnection during islanded operation
- Prepare the NC RfG measurement and compliance test report and submit it to the DSO for review
- Provide additional information and respond to the DSO’s comments, if required
- Obtain DSO approval of the compliance report
- Prepare the PGMD application
- Submit the PGMD application together with the approved compliance report
- Obtain the final operational authorization for the generating installation
- Obtain an amendment to the Distribution Agreement, if required due to circumstances beyond the applicant’s control